With our project team established and ready to commence work on The Terraces at Paddington, we will be posting updates to keep you informed on progress and to provide you with any other important information you may need to know as construction proceeds.

March 2018

Sydney aerial showing The Terraces location

Welcome to the 14th edition of the ‘The Terraces’ project newsletter. With Stage 1 now complete and the next phase of works in full swing, we will continue to publish this newsletter on a regular basis to keep you updated on what is happening on site and provide you with any other important information you may need to know as construction progresses.

Latest Events and Key Dates 29-Mar-2018

February 2018 – Topping out of the Heritage and Gatekeepers buildings. Remaining structural slabs were poured. March 2018 – Stage 2 ILU Sales Launch. March 2018 – Removal of temporary bracing on Cooper St and in the Heritage building. .. continue reading

Recent Milestones 29-Mar-2018

Stage 2 Basement excavation and piling works are all but complete. Stage 2 concrete structure has commenced, with the first slab on ground poured in the south-west corner of the MacCormick building footprint. Concrete structure and steel .. continue reading

Traffic Changes 29-Mar-2018

Pedestrian and vehicle access off Brown St has been reconfigured. New signage is provided. Bracing and scaffold is being progressively removed along Cooper St, allowing for road repair and re-widening... continue reading

Upcoming Site Activity 29-Mar-2018

A concrete placing boom has been installed on site. This will pump concrete as the Stage 2 structure progresses upwards. Concrete supply trucks will be arriving on site regularly on pour days. Façade and internal fit out works are on.. continue reading


EASTER SHUTDOWN

The site will be closed over the Easter long weekend, from Friday 30th March through to Monday 2nd April inclusive. We wish all of our neighbours a happy easter break.