Construction updates The Terraces at Paddington, Sydney

Presbyterian Aged Care retirement village Sydney

With our project team established and ready to commence work on The Terraces at Paddington, we will be posting updates to keep you informed on progress and to provide you with any other important information you may need to know as construction proceeds.

September 2018

Sydney aerial showing The Terraces location

Welcome to the 16th edition of the ‘The Terraces’ project newsletter. With the Stage 1 and 1A buildings now complete and the final phase of works in full swing, we will publish this newsletter on a regular basis to keep you updated on what is happening on site and provide any other important information you may need to know during the final stage of construction.

Latest Events and Key Dates 10-Sep-2018

22 August MacCormick Building Top Out Final Level 9 roof slab poured 24 August Completion of Stage 1A Including the Heritage and Gatekeepers Apartments, and the Pocket Park at the corner of Cooper and Brown St 27 September Off.. continue reading

Recent Milestones 10-Sep-2018

The Scottish and Gatekeepers buildings, Pocket Park and surrounding landscaped areas were completed and handed over on 24th August. All construction fencing and jersey kerbs have been removed along Cooper St. A new temporary fence has been inst.. continue reading

Stage 1A Completed! 10-Sep-2018

We look forward to welcoming the new Scottish and Gatekeepers residents in coming months. .. continue reading

Upcoming Site Activity 10-Sep-2018

Façade and fit out works will continue in the MacCormick building, progressing upward. Masonry and excavation works will continue in the central terraces. Traffic controllers will continue to manage delivery truck movements through the main gat.. continue reading