Recent Milestones 19-Nov-2018

  • 8 new residents have now moved in to the Stage 1A Scottish and Gatekeepers apartments, following completion of the two buildings in August.
  • In Stage 2, services rough in is complete in all 52 apartments, and services fit-off is now underway.
  • Tiling, joinery installation and painting is complete on Levels 2 and 3.
  • Fa├žade brickwork, cladding and window installation is complete up to Level 5.
  • Scaffold stripping has commenced on the south, east and west elevations.
  • Backfilling and masonry is ongoing in the central terraced gardens.
  • External works have commenced around the perimeter of the MacCormick building and at the main entry to site.