Construction progress and project staging 17-Nov-2015

Construction progress Brookfield Multiplex began work onsite for Stage 1 in November 2015. Construction activity over the coming weeks includes site security fencing and hoardings, services diversions, establishment of temporary sit.. continue reading

Project overview and location 17-Nov-2015

Project overview The Terraces at Paddington project team is excited to begin construction on the new village. The project will involve the construction of 70 new independent living units in four apartment blocks; replacement of the exis.. continue reading

Road closures and disruptions 17-Nov-2015

Safe access to the existing Residential Aged Care Facility for pedestrians and vehicles throughout the project is of key importance to the project team and we have carefully considered how we will minimise disruption to current users during the p.. continue reading

Upcoming milestones 17-Nov-2015

November 2015 - Demolition March 2016 - Bulk Excavation May 2016 - Tower crane installation.. continue reading