July-August 2016 17-Nov-2016

Welcome to the sixth edition of the Brookfield Multiplex ‘The Terraces’ project newsletter. With works on the new Aged Care Facility and Independent Living Units in full swing we will be publishing this newsletter on a regular basis to keep you informed on the project’s progress and to provide you with any other important information you may need to know as construction progresses. A community update information session is being scheduled to occur in the next few months.

Community 15-Aug-2016

Glenmore Road Public School recently participated in our ‘Name the Crane’ competition, in which kindergarten students submitted a name for the crane and the winners were awarded with prizes including a kid-sized construction hard hat, high-v.. continue reading

Construction progress 15-Aug-2016

Over the past few months, the tower crane has been erected, bulk excavation has been progressing and footings for the new structures adjacent to Stephen Street have commenced. Upcoming activities include finishing the remaining excavation, co.. continue reading

Scottish Hospital Update 15-Aug-2016

Following events involving the Scottish Hospital Heritage Building, road closures were required on Cooper Street for access to install steel bracing. Temporary traffic lights and barriers remain in replace on Cooper Street until such time that th.. continue reading

Upcoming milestones 15-Aug-2016

4 August 2016 - In-ground services installation 10 August 2016 - Basement slab concrete pour 12 August 2016 - Main structure excavation complete.. continue reading

View a PDF of the July-August newsletter