July 2017 Newsletter 28-Jul-2017

Welcome to the tenth edition of the Multiplex ‘The Terraces’ project newsletter. With works on the new Aged Care Facility and Independent Living Units in full swing we will continue to publish this newsletter on a regular basis to keep you informed on the project’s progress and to provide you with any other important information you may need to know as construction progresses.

Construction Progress 28-Jul-2017

The RACF building fitout and façade works are now well underway with masonry up to level 7 and sheeting of internal walls up to level 5. The Stephen Street building fitout and façade works are substantially complete and services commis.. continue reading

Independant Living 28-Jul-2017

The Stephen Street Independent Living Units (ILU) are nearing completion with services commissioning commencing in July. Below photo shows a typical ILU nearing completion. .. continue reading

Resident Presentation 28-Jul-2017

Multiplex and PAC held a presentation for the purchasers of the new ILU’s at the Vibe hotel in July. Multiplex provided an update on the construction status, clarified apartment features and explained the staged construction of the project. .. continue reading

Road Closures & Disruptions 28-Jul-2017

The plumbing subcontractor will be undertaking a connection to the water mains on Neild Avenue. It is anticipated that the works may involve closing one lane of Neild Avenue during working hours. Also, the NBN subcontractor will be undertaking a .. continue reading

Upcoming Milestones 28-Jul-2017

July - RACF building fitout and façade works ongoing. July - Landscape and external works commencing. July - Heritage building restoration and adaptive works ongoing. August - Stephen Street building fitout and façade works complete.. continue reading

View a PDF of the July 2017 newsletter