Construction Progress 28-Jul-2017

The RACF building fitout and fac╠žade works are now well underway with masonry up to level 7 and sheeting of internal walls up to level 5.

The Stephen Street building fitout and fac╠žade works are substantially complete and services commissioning is underway.

The construction of the landscape and external works will commence in July including the Dementia Garden construction.

Restoration and adaptive works in the Heritage building are ongoing.